Costa Maya News
New articles:
Costa Maya port to Reopen in July
Costa Maya Reopening Three Months Ahead of Schedule
Free veterinary clinic on the Costa Maya
The Malecon in Mahahual is progressing
Construction of Malecon has started
Puerto Costa Maya to reopen in September 2008
Felix is a Huricane catagory 2 and heading for Belize
Dean 2007 to hit the Mexican Caribean coast
Xcalak 107th Aniversary - history
Xcalak 107th Aniversary activities
Tulum airport becoming reality
Hotel Arrecifes Costa Maya opened
Uchben Kah opened by Félix González Canto
Past articles:
Costa Maya Reopening Three Months Ahead of Schedule
The Port of Costa Maya, which took a major hit from Hurricane Dean in August 2007, is on the rebound and coming back faster than anticipated.
According to an official statement, the reconstruction of berthing spaces one and two is now 58 percent complete -- and both will be ready to receive cruise ships three months earlier than originally expected (no exact date was given). A third position is also being rebuilt, to be finished after the summertime reopening. In the interim, Costa Maya will only welcome ships at its fully operational berths. The port will not tender in additional passengers, in order to focus on reconstruction and recovery while still operating at two-thirds capacity.
At this point, we do not know which cruise lines will be first to return. Negotiations are underway, according to the statement, and a new schedule should be finalized and available by the beginning of February.
Back
02.02.2008.